Thursday, March 5, 2009

Interior wood work







Interior wood work is being done mostly with famous Nilambur teak.Doors and windows are also done in Nilambur Teak.Pictures show charupady work in teak

Putty work







Birla white putty is applied on both interior and exterior walls.This will give protection for walls from moisture and possible cracks in future.Basically it will strengthen walls in addition to giving smooth finish thereby removing any imperfections during plastering.Pictures show exterior and interior with design plastered areas

Monday, February 2, 2009

Wall tile laying-toilets


Wall and floor tile laying for toilets is over.Granite slab and tile laying is also getting completed.Picture shows wall tile laid on toilet walls

Wednesday, January 21, 2009

Mukhappu in the front side


Picture shows Mukhappu in the front side after clay tile laying on slope roof.Round columns after design plastering and putty work can be seen

Tile laying on slope roof


Picture shows view of the house after tile laying on slope roofs and slope sunshades.Birla white putty work is in progress for outside and inside walls

Tuesday, December 23, 2008

One more view clay tile laying on floor


Picture shows one more view of clay tile laid on floors after polishing

Clay tile laying on Flat roof


Clay tile is laid on flat roof terraces in ground floor and first floor.Picture shows clay tile laid.Clay tile is less costly compared to granite or ceramic tiles.It gives good appearance,eco friendly and healthy for those who uses the house